P6V7单机版(stand-alone模式)安装说明

1、全新安装P6V7客户端,双击setup.exe。一般选择Construction and Engineering
2、选择stand-alone模式,安装程序会问你两次程序的安装目录,第一次是主程序,第二次是数据库,最好安装在同一个盘符且空间最好1G以上(会自动安装数据库),同时保证C盘剩余空间最好1G以上。
3、自动安装Oracle

 
2012-01-30 11:29


 
2012-01-14 09:58

1 export a xls from current schedule, select the activies relationship, and new a fliter which condition are:

A status is not equal to  not start

B completed % is bigger than 0

2 open a schedule which have no progress,and copy new schedule's wbs id

3 open the excel sheet,replace old wbs id to new schedule's wbs id

4 import the excel to new schedule

 

 

we can do this only because a

 
2012-01-09 09:22

nett    6 days calader +public holidays-No delay allowance 100
target  6 days calader                 -12-15% delay allowance
gross(Contract)   6 days calader       -18-21% delay allowance

 
2012-01-06 11:36


 
2011-12-24 15:46


 
2011-12-19 09:33

   

\

 

 
2011-11-02 09:37

回成都已经半年,这段时间的生活应该是有史以来最好的。

有美女看,有啤酒喝,有时候有朋友过来玩。

可惜,马上又要离开。

不过我还是会回来的。

 

 

工作上这段时间脱离了计划工程师的轨道。

以专家身份进来,然后实际是个打杂的,兼职excel杂工。

在专业上是学到东西最少的。

不过涉及了资金计划,内部控制流程,项目采购流程。

复习了权重,月报。

 

这边是做政治的,不是

 
2011-09-30 17:03

完成了第一个目标。

买在成都极其偏远的地方,等地铁修好估计方便些。

下个目标是注册公司,希望明年初能完成。

公司名暂定:milestone,美尔斯通?

 
2011-09-13 11:39

一、报批阶段:
1、项目设立申请(发改委)—→
2、发放投资许可证及批复(发改委)—→
3、购买土地(国土局)—→
4、发放用地许可证(国土局)—→
5、申请建设用地规划(规划局)—→
6、发放建设用地规划许可证(规划局)—→
7、施工图设计阶段—→
8、召开项目方案评审会(建设局)—→
9、申请施工图审(建设局)—→
10、发放施工图设计文件审查批准书(建设局)—→
11、申请施工图防火审核(消防队)—→
12、发放建筑设计防火审核意见(消防队)—→
13、申请项目环境审批(

 
2011-07-26 11:05


 
2011-07-26 11:01


 
2011-07-19 15:47




 
2011-07-18 14:52



 
     
 
 
个人档案
 
lexno
男, 
四川 成都 
 
   
 
文章分类
 
 
 
 
 
 
 
 
     
 
最新评论
 
     
 
好友最新文章
 
     
 
订阅我的空间
 
已有人次访问本空间
 
订阅RSS  什么是RSS?

您也想拥有这样的空间?请点此申请。
     

帮助中心  |  空间客服  |  投诉中心  |  空间协议
©2012 Baidu